District of West Vancouver
How to get a building permit in West Vancouver, BC
Where to apply, what West Vancouver asks for, what it costs, and who issues electrical and gas permits — with links to the city's own forms.
Where to apply in West Vancouver
Document Upload Centre (custom in-house portal on hhapps.westvancouver.ca/hhapps/DocuPro80000/index.aspx) - mandatory for building permits since April 15, 2021; emailed submissions are NOT accepted. E-Apply portal is available for TRADE permits only (requires an active issued building permit). Account portal is MyDistrict (eservices.westvancouver.ca).
Official District of West Vancouver permit pagePermits and Inspections Department: permits@westvancouver.ca; Municipal Hall, 750 17th Street, West Vancouver, BC V7V 3T3; general 604-925-7000; Bylaws/licensing 604-925-7152
Who issues electrical and gas permits
SPLIT: West Vancouver runs its OWN electrical permit and inspection program - electrical permits are issued by the District and inspected by a District Electrical Safety Officer (NOT Technical Safety BC). However, West Vancouver does NOT issue GAS permits - gas permits go to Technical Safety BC (technicalsafetybc.ca).
- electrical
- District of West Vancouver
- gas
- Technical Safety BC
Step by step in West Vancouver
- 1
Confirm zoning before anything else
Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — West Vancouver won't issue until land use is settled.
- 2
Work out which permits you need
Structural work needs a building permit from District of West Vancouver. Electrical and gas are separate and are issued by SPLIT: West Vancouver runs its OWN electrical permit and inspection program - electrical permits are issued by the District and inspected by a District Electrical Safety Officer (NOT Technical Safety BC). Plumbing is usually part of the building permit.
- 3
Prepare drawings and documents
District of West Vancouver asks for: Submit via the Document Upload Centre (emailed submissions not accepted); incomplete submissions are refused; Building Permit Application Form and Checklist for Single-Family and Duplex Dwellings (separate Demolition Permit Application if demolishing); Registered Owner's Authorization Form (if applicant is not the registered owner); Housing Form (required for new single family/duplex/secondary suite/coach house building and demolition applications, per Provincial Housing Supply Act); Landscaping Checklist and commitment letter by a landscape architect/licensed contractor (new single-family dwellings, since Dec 1 2025); Structural Schedule B and other registered-professional assurances; drawings must be PDF, to scale, high-resolution, combined per discipline and named accordingly (e.g. 'Structural Schedule B'); BC Energy Step Code / Zero Carbon compliance reports (Part 9 and Part 3 energy compliance tools); Design Intent Letter & Design Verification Report for BCBC Part 10; Development Cost Charges form for new buildings/additions; Fire Safety Plan required for demolition and construction sites; Demolition Material Recycling and Disposal Report (statutory declaration); Development Permit and/or Environmental Development Permit may be required BEFORE a building permit (e.g. within a DPA, new coach house, or Wildfire Hazard DPA); Summary of Zoning Variances (only if Board of Variance review needed); Electrical permits must be taken out by a provincially-qualified contractor with a valid West Vancouver business licence unless the owner satisfies the electrical inspector of competence; Electrical Declaration Form required with each inspection request.
- 4
Submit your application
Document Upload Centre (custom in-house portal on hhapps.westvancouver.ca/hhapps/DocuPro80000/index.aspx) - mandatory for building permits since April 15, 2021; emailed submissions are NOT accepted. E-Apply portal is available for TRADE permits only (requires an active issued building permit). Account portal is MyDistrict (eservices.westvancouver.ca).
- 5
Pay the permit fee
Building permit fees are based on 'Building Construction Value' as defined in Building Bylaw No. 5340, 2025 (tiered fee schedule). Value of electrical works = 4.0% of building construction value (contractor may declare a different value). Re-inspection and revision surcharges apply (first free, then $150/$300/$600 escalating). Confirm the current schedule with West Vancouver before you budget.
- 6
Plan review, then build to inspections
The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.
What West Vancouver asks for
- Submit via the Document Upload Centre (emailed submissions not accepted); incomplete submissions are refused
- Building Permit Application Form and Checklist for Single-Family and Duplex Dwellings (separate Demolition Permit Application if demolishing)
- Registered Owner's Authorization Form (if applicant is not the registered owner)
- Housing Form (required for new single family/duplex/secondary suite/coach house building and demolition applications, per Provincial Housing Supply Act)
- Landscaping Checklist and commitment letter by a landscape architect/licensed contractor (new single-family dwellings, since Dec 1 2025)
- Structural Schedule B and other registered-professional assurances; drawings must be PDF, to scale, high-resolution, combined per discipline and named accordingly (e.g. 'Structural Schedule B')
- BC Energy Step Code / Zero Carbon compliance reports (Part 9 and Part 3 energy compliance tools); Design Intent Letter & Design Verification Report for BCBC Part 10
- Development Cost Charges form for new buildings/additions
- Fire Safety Plan required for demolition and construction sites; Demolition Material Recycling and Disposal Report (statutory declaration)
- Development Permit and/or Environmental Development Permit may be required BEFORE a building permit (e.g. within a DPA, new coach house, or Wildfire Hazard DPA)
- Summary of Zoning Variances (only if Board of Variance review needed)
- Electrical permits must be taken out by a provincially-qualified contractor with a valid West Vancouver business licence unless the owner satisfies the electrical inspector of competence; Electrical Declaration Form required with each inspection request
Permit fees in West Vancouver
Building permit fees are based on 'Building Construction Value' as defined in Building Bylaw No. 5340, 2025 (tiered fee schedule). Value of electrical works = 4.0% of building construction value (contractor may declare a different value). Re-inspection and revision surcharges apply (first free, then $150/$300/$600 escalating).
Fees change and vary by project — confirm the current schedule with District of West Vancouver.
West Vancouver permit forms
Open a form here and fill it in without leaving the page.
Pick a form to open it here.
Permit types in West Vancouver
Electrical permit
A safety permit required before doing regulated electrical work in BC — an Installation Permit for a defined project (new wiring, upgrades, alterations), or an Operating Permit for ongoing maintenance of existing electrical equipment in larger/commercial facilities.
Plumbing permit
A trade permit (often issued separately from, or alongside, the building permit) authorizing installation, extension, or alteration of potable water, drainage-waste-vent, and connections to municipal water/sewer, verified against the BC Plumbing Code.
Demolition permit
A municipal permit to tear down or remove a building or structure, conditional on safe utility disconnections, a pre-demolition hazardous-materials (asbestos) survey and abatement, and — in many cities — recycling/deconstruction requirements backed by a refundable deposit.
Worth knowing about West Vancouver
Runs its own electrical inspection (Electrical Safety Officer) but defers GAS to Technical Safety BC. Development/Environmental Development permit often required first; Wildfire Hazard DPA and Tree Bylaw (20 cm DBH protection) affect new-build sites. Strong urban-forest/landscaping and heritage (Lower Caulfeild HCA) rules. Contractors from North Vancouver need an inter-municipal business licence.
West Vancouver permit questions
Where do I submit a building permit application in West Vancouver?
Document Upload Centre (custom in-house portal on hhapps.westvancouver.ca/hhapps/DocuPro80000/index.aspx) - mandatory for building permits since April 15, 2021; emailed submissions are NOT accepted. E-Apply portal is available for TRADE permits only (requires an active issued building permit). Account portal is MyDistrict (eservices.westvancouver.ca).
Who issues electrical and gas permits in West Vancouver?
SPLIT: West Vancouver runs its OWN electrical permit and inspection program - electrical permits are issued by the District and inspected by a District Electrical Safety Officer (NOT Technical Safety BC). However, West Vancouver does NOT issue GAS permits - gas permits go to Technical Safety BC (technicalsafetybc.ca).
How much does a building permit cost in West Vancouver?
Building permit fees are based on 'Building Construction Value' as defined in Building Bylaw No. 5340, 2025 (tiered fee schedule). Value of electrical works = 4.0% of building construction value (contractor may declare a different value). Re-inspection and revision surcharges apply (first free, then $150/$300/$600 escalating). Fees vary by project, so confirm the current schedule with District of West Vancouver before budgeting.
What do I need to apply for a building permit in West Vancouver?
District of West Vancouver asks for: Submit via the Document Upload Centre (emailed submissions not accepted); incomplete submissions are refused; Building Permit Application Form and Checklist for Single-Family and Duplex Dwellings (separate Demolition Permit Application if demolishing); Registered Owner's Authorization Form (if applicant is not the registered owner); Housing Form (required for new single family/duplex/secondary suite/coach house building and demolition applications, per Provincial Housing Supply Act); Landscaping Checklist and commitment letter by a landscape architect/licensed contractor (new single-family dwellings, since Dec 1 2025); Structural Schedule B and other registered-professional assurances; drawings must be PDF, to scale, high-resolution, combined per discipline and named accordingly (e.g. 'Structural Schedule B'); BC Energy Step Code / Zero Carbon compliance reports (Part 9 and Part 3 energy compliance tools); Design Intent Letter & Design Verification Report for BCBC Part 10; Development Cost Charges form for new buildings/additions; Fire Safety Plan required for demolition and construction sites; Demolition Material Recycling and Disposal Report (statutory declaration); Development Permit and/or Environmental Development Permit may be required BEFORE a building permit (e.g. within a DPA, new coach house, or Wildfire Hazard DPA); Summary of Zoning Variances (only if Board of Variance review needed); Electrical permits must be taken out by a provincially-qualified contractor with a valid West Vancouver business licence unless the owner satisfies the electrical inspector of competence; Electrical Declaration Form required with each inspection request.
Anything else to know about permits in West Vancouver?
Runs its own electrical inspection (Electrical Safety Officer) but defers GAS to Technical Safety BC. Development/Environmental Development permit often required first; Wildfire Hazard DPA and Tree Bylaw (20 cm DBH protection) affect new-build sites. Strong urban-forest/landscaping and heritage (Lower Caulfeild HCA) rules. Contractors from North Vancouver need an inter-municipal business licence.
Sources
- https://westvancouver.ca/business-development/building-development/building-permits-inspections
- https://westvancouver.ca/business-development/building-development/building-permits-inspections/building-permits-single-family
- https://westvancouver.ca/home-building-property/permits-licences/building-renovation/electrical-permits
- https://westvancouver.ca/business-development/building-development/building-permits-inspections/regulations-fees
- https://westvancouver.ca/business-development/building-development/building-permits-inspections/permits-licences/additional-forms
General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with District of West Vancouver before you build.