Where to apply in Vernon

MyCity / Tempest 'Prospero' e-Apply online portal (Tempest software). Submit online at https://ecommerce2.vernon.ca/TempestApps/eapply/prospero/dashboard/ (account login at https://ecommerce2.vernon.ca/TempestAPPS/LoginManager/). In-person alternative at Community Services Building, 3001 32nd Avenue. All drawings/documents must be uploaded as PDF before an application is accepted.

Official City of Vernon permit page

Building/permit counter email buildingcounter@vernon.ca. Community Services Building, 3001 32nd Avenue, Vernon, BC V1T 2L8. Main 250-545-1361; inspections 250-550-3592.

Who issues electrical and gas permits

Technical Safety BC issues ALL electrical and gas permits. Vernon is NOT on TSBC's delegated-municipality list (unlike Vancouver/Surrey/Burnaby etc.), so the city does not run its own electrical or gas program. Apply through technicalsafetybc.ca.

electrical
Technical Safety BC
gas
Technical Safety BC

Step by step in Vernon

  1. 1

    Confirm zoning before anything else

    Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — Vernon won't issue until land use is settled.

  2. 2

    Work out which permits you need

    Structural work needs a building permit from City of Vernon. Electrical and gas are separate and are issued by Technical Safety BC issues ALL electrical and gas permits. Plumbing is usually part of the building permit.

  3. 3

    Prepare drawings and documents

    City of Vernon asks for: Digital drawings and all documentation in PDF format before application is accepted; Building Permit Checklist (PDF provided by city); Site plan and project documentation vary by project type; Security deposit required in addition to the permit fee; Development permit may be required before the building permit; Complex projects (per BC Building Code Division A, Section 1.3.3) trigger registered-professional involvement / Schedule A & B.

  4. 4

    Submit your application

    MyCity / Tempest 'Prospero' e-Apply online portal (Tempest software). Submit online at https://ecommerce2.vernon.ca/TempestApps/eapply/prospero/dashboard/ (account login at https://ecommerce2.vernon.ca/TempestAPPS/LoginManager/). In-person alternative at Community Services Building, 3001 32nd Avenue. All drawings/documents must be uploaded as PDF before an application is accepted.

  5. 5

    Pay the permit fee

    Application intake fee: $150 for non-complex projects, $250 for complex projects (complexity per BC Building Code Div A, s.1.3.3). A security deposit is charged on top. 2.4% credit-card surcharge. Full fee schedule in Fees and Charges Bylaw No. 3909; building regulated under Building Bylaw No. 5900. Confirm the current schedule with Vernon before you budget.

  6. 6

    Plan review, then build to inspections

    The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.

What Vernon asks for

  • Digital drawings and all documentation in PDF format before application is accepted
  • Building Permit Checklist (PDF provided by city)
  • Site plan and project documentation vary by project type
  • Security deposit required in addition to the permit fee
  • Development permit may be required before the building permit
  • Complex projects (per BC Building Code Division A, Section 1.3.3) trigger registered-professional involvement / Schedule A & B

Permit fees in Vernon

Application intake fee: $150 for non-complex projects, $250 for complex projects (complexity per BC Building Code Div A, s.1.3.3). A security deposit is charged on top. 2.4% credit-card surcharge. Full fee schedule in Fees and Charges Bylaw No. 3909; building regulated under Building Bylaw No. 5900.

Fees change and vary by project — confirm the current schedule with City of Vernon.

Vernon permit forms

Open a form here and fill it in without leaving the page.

Pick a form to open it here.

Permit types in Vernon

Plumbing permit

A trade permit (often issued separately from, or alongside, the building permit) authorizing installation, extension, or alteration of potable water, drainage-waste-vent, and connections to municipal water/sewer, verified against the BC Plumbing Code.

Demolition permit

A municipal permit to tear down or remove a building or structure, conditional on safe utility disconnections, a pre-demolition hazardous-materials (asbestos) survey and abatement, and — in many cities — recycling/deconstruction requirements backed by a refundable deposit.

Worth knowing about Vernon

Development permit may be required before a building permit. Heritage Retention Grant program exists for heritage properties. Occupancy Permit issued only after final inspections pass. Pre-application consultation with Planning & Community Services strongly recommended.

Vernon permit questions

Where do I submit a building permit application in Vernon?

MyCity / Tempest 'Prospero' e-Apply online portal (Tempest software). Submit online at https://ecommerce2.vernon.ca/TempestApps/eapply/prospero/dashboard/ (account login at https://ecommerce2.vernon.ca/TempestAPPS/LoginManager/). In-person alternative at Community Services Building, 3001 32nd Avenue. All drawings/documents must be uploaded as PDF before an application is accepted.

Who issues electrical and gas permits in Vernon?

Technical Safety BC issues ALL electrical and gas permits. Vernon is NOT on TSBC's delegated-municipality list (unlike Vancouver/Surrey/Burnaby etc.), so the city does not run its own electrical or gas program. Apply through technicalsafetybc.ca.

How much does a building permit cost in Vernon?

Application intake fee: $150 for non-complex projects, $250 for complex projects (complexity per BC Building Code Div A, s.1.3.3). A security deposit is charged on top. 2.4% credit-card surcharge. Full fee schedule in Fees and Charges Bylaw No. 3909; building regulated under Building Bylaw No. 5900. Fees vary by project, so confirm the current schedule with City of Vernon before budgeting.

What do I need to apply for a building permit in Vernon?

City of Vernon asks for: Digital drawings and all documentation in PDF format before application is accepted; Building Permit Checklist (PDF provided by city); Site plan and project documentation vary by project type; Security deposit required in addition to the permit fee; Development permit may be required before the building permit; Complex projects (per BC Building Code Division A, Section 1.3.3) trigger registered-professional involvement / Schedule A & B.

Anything else to know about permits in Vernon?

Development permit may be required before a building permit. Heritage Retention Grant program exists for heritage properties. Occupancy Permit issued only after final inspections pass. Pre-application consultation with Planning & Community Services strongly recommended.

Sources

General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with City of Vernon before you build.