How to get a building permit in Vancouver, BC

Where to apply, what Vancouver asks for, what it costs, and who issues electrical and gas permits — with links to the city's own forms.

Where to apply in Vancouver

Vancouver Permit Office (VPO) / online permit account — https://vpo.vancouver.ca (POSSE self-service system at https://plposweb.vancouver.ca). Apply/register at https://vancouver.ca/permits/apply. Most applications, payments, and inspection requests are handled 24/7 in the online permit account.

Official City of Vancouver permit page

Development & Building Services Centre, 515 West 10th Ave, Ground Floor, Vancouver BC V5Z 4A8. Phone 604-873-7611; inspection booking 604-873-7485.

Who issues electrical and gas permits

UNIQUE IN BC: The City of Vancouver runs its OWN electrical permit and inspection program (NOT Technical Safety BC) — Vancouver operates under the Vancouver Charter with its own Building By-law and Electrical By-law No. 5563. To pull an electrical permit you must be a licensed electrical contractor holding a valid City of Vancouver (or inter-municipal) business licence; limited owner/homeowner electrical permits are available for detached single-family homes. Vancouver ALSO runs its own plumbing and fire-sprinkler permit programs. GAS is the exception — gas permits are NOT a City of Vancouver program; gas installations are permitted/inspected by Technical Safety BC (provincial). So per-city: electrical = City of Vancouver; plumbing = City of Vancouver; sprinkler = City of Vancouver; gas = Technical Safety BC.

electrical
City of Vancouver
Sending this to Technical Safety BC instead won't get forwarded — it starts over. On a service upgrade that also pushes out your BC Hydro reconnect, usually the longest lead time on the whole job.
gas
City of Vancouver
Sending this to Technical Safety BC instead won't get forwarded — it starts over, and gas work can't be inspected or turned on until the right authority has issued the permit.

Step by step in Vancouver

  1. 1

    Confirm zoning before anything else

    Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — Vancouver won't issue until land use is settled.

  2. 2

    Work out which permits you need

    Structural work needs a building permit from City of Vancouver. Electrical and gas are separate and are issued by UNIQUE IN BC: The City of Vancouver runs its OWN electrical permit and inspection program (NOT Technical Safety BC) — Vancouver operates under the Vancouver Charter with its own Building By-law and Electrical By-law No. Plumbing is usually part of the building permit.

  3. 3

    Prepare drawings and documents

    City of Vancouver asks for: Online permit account required to submit, share documents, communicate with reviewers, pay, and request inspections; Site plan / plot plan; Floor plans (existing and proposed); Building elevations and sections; Energy compliance documentation / BC Energy Step Code (Vancouver has its own energy requirements in the Building By-law; required on larger projects, e.g. over ~$150K value); Structural drawings stamped/sealed by a professional engineer for load-bearing/complex work (Letters of Assurance); Geotechnical report where applicable (hillside/soils); Owner authorization if the applicant is not the registered owner; Home warranty insurance (BC Homeowner Protection) enrolment for new homes, or an owner-builder exemption.

  4. 4

    Submit your application

    Vancouver Permit Office (VPO) / online permit account — https://vpo.vancouver.ca (POSSE self-service system at https://plposweb.vancouver.ca). Apply/register at https://vancouver.ca/permits/apply. Most applications, payments, and inspection requests are handled 24/7 in the online permit account.

  5. 5

    Pay the permit fee

    Set by the annual Schedule of Fees for Development & Building Related Permits (2026 schedule PDF at vancouver.ca/files/cov/vancouver-development-building-permit-fees.pdf). Building permit fees are TIERED by project construction value (not a flat per-$1,000 rate) — a base fee per value tier plus an incremental rate per $1,000 of value above the tier threshold. Electrical, plumbing, gas-adjacent and sprinkler permits carry their own separate fee lines. Confirm the current schedule with Vancouver before you budget.

  6. 6

    Plan review, then build to inspections

    The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.

What Vancouver asks for

  • Online permit account required to submit, share documents, communicate with reviewers, pay, and request inspections
  • Site plan / plot plan
  • Floor plans (existing and proposed)
  • Building elevations and sections
  • Energy compliance documentation / BC Energy Step Code (Vancouver has its own energy requirements in the Building By-law; required on larger projects, e.g. over ~$150K value)
  • Structural drawings stamped/sealed by a professional engineer for load-bearing/complex work (Letters of Assurance)
  • Geotechnical report where applicable (hillside/soils)
  • Owner authorization if the applicant is not the registered owner
  • Home warranty insurance (BC Homeowner Protection) enrolment for new homes, or an owner-builder exemption

Permit fees in Vancouver

Set by the annual Schedule of Fees for Development & Building Related Permits (2026 schedule PDF at vancouver.ca/files/cov/vancouver-development-building-permit-fees.pdf). Building permit fees are TIERED by project construction value (not a flat per-$1,000 rate) — a base fee per value tier plus an incremental rate per $1,000 of value above the tier threshold. Electrical, plumbing, gas-adjacent and sprinkler permits carry their own separate fee lines.

Fees change and vary by project — confirm the current schedule with City of Vancouver.

Vancouver permit forms

Open a form here and fill it in without leaving the page.

Pick a form to open it here.

Worth knowing about Vancouver

Vancouver is legally distinct from the rest of BC: BC Codes do NOT apply — the Vancouver Building By-law governs, and the City runs its own electrical, plumbing and sprinkler inspection programs (a major difference from Surrey/Burnaby/Richmond where those are shared with the province). A development permit is frequently required BEFORE the building permit for change-of-use, new builds, and heritage/character areas. Development & Building Services Centre: 515 West 10th Avenue, Ground Floor, Vancouver, BC V5Z 4A8.

Vancouver permit questions

Where do I submit a building permit application in Vancouver?

Vancouver Permit Office (VPO) / online permit account — https://vpo.vancouver.ca (POSSE self-service system at https://plposweb.vancouver.ca). Apply/register at https://vancouver.ca/permits/apply. Most applications, payments, and inspection requests are handled 24/7 in the online permit account.

Who issues electrical and gas permits in Vancouver?

UNIQUE IN BC: The City of Vancouver runs its OWN electrical permit and inspection program (NOT Technical Safety BC) — Vancouver operates under the Vancouver Charter with its own Building By-law and Electrical By-law No. 5563. To pull an electrical permit you must be a licensed electrical contractor holding a valid City of Vancouver (or inter-municipal) business licence; limited owner/homeowner electrical permits are available for detached single-family homes. Vancouver ALSO runs its own plumbing and fire-sprinkler permit programs. GAS is the exception — gas permits are NOT a City of Vancouver program; gas installations are permitted/inspected by Technical Safety BC (provincial). So per-city: electrical = City of Vancouver; plumbing = City of Vancouver; sprinkler = City of Vancouver; gas = Technical Safety BC.

How much does a building permit cost in Vancouver?

Set by the annual Schedule of Fees for Development & Building Related Permits (2026 schedule PDF at vancouver.ca/files/cov/vancouver-development-building-permit-fees.pdf). Building permit fees are TIERED by project construction value (not a flat per-$1,000 rate) — a base fee per value tier plus an incremental rate per $1,000 of value above the tier threshold. Electrical, plumbing, gas-adjacent and sprinkler permits carry their own separate fee lines. Fees vary by project, so confirm the current schedule with City of Vancouver before budgeting.

What do I need to apply for a building permit in Vancouver?

City of Vancouver asks for: Online permit account required to submit, share documents, communicate with reviewers, pay, and request inspections; Site plan / plot plan; Floor plans (existing and proposed); Building elevations and sections; Energy compliance documentation / BC Energy Step Code (Vancouver has its own energy requirements in the Building By-law; required on larger projects, e.g. over ~$150K value); Structural drawings stamped/sealed by a professional engineer for load-bearing/complex work (Letters of Assurance); Geotechnical report where applicable (hillside/soils); Owner authorization if the applicant is not the registered owner; Home warranty insurance (BC Homeowner Protection) enrolment for new homes, or an owner-builder exemption.

Anything else to know about permits in Vancouver?

Vancouver is legally distinct from the rest of BC: BC Codes do NOT apply — the Vancouver Building By-law governs, and the City runs its own electrical, plumbing and sprinkler inspection programs (a major difference from Surrey/Burnaby/Richmond where those are shared with the province). A development permit is frequently required BEFORE the building permit for change-of-use, new builds, and heritage/character areas. Development & Building Services Centre: 515 West 10th Avenue, Ground Floor, Vancouver, BC V5Z 4A8.

Sources

General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with City of Vancouver before you build.