How to get a building permit in Squamish, BC

Where to apply, what Squamish asks for, what it costs, and who issues electrical and gas permits — with links to the city's own forms.

Where to apply in Squamish

Building permit applications are submitted IN PERSON at Municipal Hall (10 a.m.-3 p.m., Mon-Fri; note applications are not reviewed 10 a.m.-2:30 p.m.). The district has an 'eApply' online portal but only for select items (building information requests, pre-applications, water on/off, residential demolitions) - not full building permits yet. Squamish is also listed on the provincial Building Permit Hub (buildingpermit.gov.bc.ca).

Official District of Squamish permit page

Development Services Department, Municipal Hall, 37955 Second Avenue, P.O. Box 310, Squamish, BC V8B 0A3. General 604-892-5217; wait-times line 604-815-6872; Community Planning 604-815-5002.

Who issues electrical and gas permits

Technical Safety BC issues ALL electrical and gas permits. Squamish is NOT on TSBC's delegated-municipality list, so the district does not run its own electrical or gas program. Apply through technicalsafetybc.ca.

electrical
Technical Safety BC
gas
Technical Safety BC

Step by step in Squamish

  1. 1

    Confirm zoning before anything else

    Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — Squamish won't issue until land use is settled.

  2. 2

    Work out which permits you need

    Structural work needs a building permit from District of Squamish. Electrical and gas are separate and are issued by Technical Safety BC issues ALL electrical and gas permits. Plumbing is usually part of the building permit.

  3. 3

    Prepare drawings and documents

    District of Squamish asks for: Complete application reviewed by a Development Services Representative at intake; application fee paid at submission; Residential Building Permit Checklist / Commercial Document Checklist (defines required drawings & docs); 'Minimum Requirements for Application Drawings' standard; BC Energy Step Code energy compliance / design verification reports; Owner authorization forms; Alternative Solutions Summary Information where certified professionals are used; Off-site servicing must be confirmed (or a Servicing Agreement executed) before permit issuance; Civic address must be posted and visible or inspections will not occur.

  4. 4

    Submit your application

    Building permit applications are submitted IN PERSON at Municipal Hall (10 a.m.-3 p.m., Mon-Fri; note applications are not reviewed 10 a.m.-2:30 p.m.). The district has an 'eApply' online portal but only for select items (building information requests, pre-applications, water on/off, residential demolitions) - not full building permits yet. Squamish is also listed on the provincial Building Permit Hub (buildingpermit.gov.bc.ca).

  5. 5

    Pay the permit fee

    Tiered application fee by construction value: $200 (< $100,000), $500 (> $100,000, excluding tenant improvements & accessory dwelling units), $1,000 (> $1,000,000), $3,000 (> $5,000,000). Other charges may apply: offsite service connections, damage deposits, Lot Grading deposit, Development Cost Charges, Service Agreement charges. Details in the Fees and Charges Amendment Bylaw. In-person credit card accepted up to $25,000 (2.4% surcharge) for some permits. Confirm the current schedule with Squamish before you budget.

  6. 6

    Plan review, then build to inspections

    The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.

What Squamish asks for

  • Complete application reviewed by a Development Services Representative at intake; application fee paid at submission
  • Residential Building Permit Checklist / Commercial Document Checklist (defines required drawings & docs)
  • 'Minimum Requirements for Application Drawings' standard
  • BC Energy Step Code energy compliance / design verification reports
  • Owner authorization forms
  • Alternative Solutions Summary Information where certified professionals are used
  • Off-site servicing must be confirmed (or a Servicing Agreement executed) before permit issuance
  • Civic address must be posted and visible or inspections will not occur

Permit fees in Squamish

Tiered application fee by construction value: $200 (< $100,000), $500 (> $100,000, excluding tenant improvements & accessory dwelling units), $1,000 (> $1,000,000), $3,000 (> $5,000,000). Other charges may apply: offsite service connections, damage deposits, Lot Grading deposit, Development Cost Charges, Service Agreement charges. Details in the Fees and Charges Amendment Bylaw. In-person credit card accepted up to $25,000 (2.4% surcharge) for some permits.

Fees change and vary by project — confirm the current schedule with District of Squamish.

Permit types in Squamish

Building permit

The core municipal approval to legally construct, add to, or structurally alter a building, issued after plan review confirms compliance with the BC Building Code and local bylaws.

Worth knowing about Squamish

Development-permit-first: if the project needs a Zoning Bylaw Amendment or Land Development Permit, those approvals must be issued BEFORE submitting the building permit. A Servicing Agreement for off-site services (water, sanitary, storm) may be required before permit issuance. Building applications cannot be reviewed 10 a.m.-2:30 p.m.

Squamish permit questions

Where do I submit a building permit application in Squamish?

Building permit applications are submitted IN PERSON at Municipal Hall (10 a.m.-3 p.m., Mon-Fri; note applications are not reviewed 10 a.m.-2:30 p.m.). The district has an 'eApply' online portal but only for select items (building information requests, pre-applications, water on/off, residential demolitions) - not full building permits yet. Squamish is also listed on the provincial Building Permit Hub (buildingpermit.gov.bc.ca).

Who issues electrical and gas permits in Squamish?

Technical Safety BC issues ALL electrical and gas permits. Squamish is NOT on TSBC's delegated-municipality list, so the district does not run its own electrical or gas program. Apply through technicalsafetybc.ca.

How much does a building permit cost in Squamish?

Tiered application fee by construction value: $200 (< $100,000), $500 (> $100,000, excluding tenant improvements & accessory dwelling units), $1,000 (> $1,000,000), $3,000 (> $5,000,000). Other charges may apply: offsite service connections, damage deposits, Lot Grading deposit, Development Cost Charges, Service Agreement charges. Details in the Fees and Charges Amendment Bylaw. In-person credit card accepted up to $25,000 (2.4% surcharge) for some permits. Fees vary by project, so confirm the current schedule with District of Squamish before budgeting.

What do I need to apply for a building permit in Squamish?

District of Squamish asks for: Complete application reviewed by a Development Services Representative at intake; application fee paid at submission; Residential Building Permit Checklist / Commercial Document Checklist (defines required drawings & docs); 'Minimum Requirements for Application Drawings' standard; BC Energy Step Code energy compliance / design verification reports; Owner authorization forms; Alternative Solutions Summary Information where certified professionals are used; Off-site servicing must be confirmed (or a Servicing Agreement executed) before permit issuance; Civic address must be posted and visible or inspections will not occur.

Anything else to know about permits in Squamish?

Development-permit-first: if the project needs a Zoning Bylaw Amendment or Land Development Permit, those approvals must be issued BEFORE submitting the building permit. A Servicing Agreement for off-site services (water, sanitary, storm) may be required before permit issuance. Building applications cannot be reviewed 10 a.m.-2:30 p.m.

Sources

General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with District of Squamish before you build.