How to get a building permit in Smithers, BC

Where to apply, what Smithers asks for, what it costs, and who issues electrical and gas permits — with links to the city's own forms.

Where to apply in Smithers

In person / email — Building Permit applications (hard copies) available at and submitted to the Town Office, 1027 Aldous Street. No online e-permitting portal noted.

Official Town of Smithers permit page

Development Services Clerk / Building Inspector, Town of Smithers — 250-847-1600; 1027 Aldous Street, PO Box 879, Smithers, BC V0J 2N0.

Who issues electrical and gas permits

Technical Safety BC — electrical and gas permits are not issued by the Town; they are handled provincially by Technical Safety BC (the page does not administer them). Confirm directly with TSBC.

electrical
Technical Safety BC
gas
Technical Safety BC

Step by step in Smithers

  1. 1

    Confirm zoning before anything else

    Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — Smithers won't issue until land use is settled.

  2. 2

    Work out which permits you need

    Structural work needs a building permit from Town of Smithers. Electrical and gas are separate and are issued by Technical Safety BC — electrical and gas permits are not issued by the Town; they are handled provincially by Technical Safety BC (the page does not administer them). Plumbing is usually part of the building permit.

  3. 3

    Prepare drawings and documents

    Town of Smithers asks for: Building Permit application form + $80 application fee; Site Plan (2 copies) showing lot shape/size, driveway, existing buildings, setbacks, project location; Building plans (2 copies): elevations, floor plans, cross sections; Site Disclosure Statement; Layout and certificates for engineered components (trusses, joists, beams); Home Owner Protection Office (BC Housing / home warranty) approval for new residences; Owner's Authorization Form (Appendix D) and Owner's Undertaking (Appendix E); Letters of Assurance from a Registered Professional (for engineered/complex work); Confirmation of Insurance (Appendix F) and required documentation for major occupancies (Appendix G).

  4. 4

    Submit your application

    In person / email — Building Permit applications (hard copies) available at and submitted to the Town Office, 1027 Aldous Street. No online e-permitting portal noted.

  5. 5

    Pay the permit fee

    $80 application fee plus construction-value fee: $6.25 per $1,000 of value up to $1,000,000, then $5.50 per $1,000 above $1,000,000. Building inspector estimates value from submitted plans. Confirm the current schedule with Smithers before you budget.

  6. 6

    Plan review, then build to inspections

    The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.

What Smithers asks for

  • Building Permit application form + $80 application fee
  • Site Plan (2 copies) showing lot shape/size, driveway, existing buildings, setbacks, project location
  • Building plans (2 copies): elevations, floor plans, cross sections
  • Site Disclosure Statement
  • Layout and certificates for engineered components (trusses, joists, beams)
  • Home Owner Protection Office (BC Housing / home warranty) approval for new residences
  • Owner's Authorization Form (Appendix D) and Owner's Undertaking (Appendix E)
  • Letters of Assurance from a Registered Professional (for engineered/complex work)
  • Confirmation of Insurance (Appendix F) and required documentation for major occupancies (Appendix G)

Permit fees in Smithers

$80 application fee plus construction-value fee: $6.25 per $1,000 of value up to $1,000,000, then $5.50 per $1,000 above $1,000,000. Building inspector estimates value from submitted plans.

Fees change and vary by project — confirm the current schedule with Town of Smithers.

Worth knowing about Smithers

Most permits issued within 20 working days depending on complexity/completeness. No permit needed for non-structural work (painting, same-size window/door swaps, fences, private sidewalks, non-structural re-roof/re-side). 2025 BC Building Code requirements apply (see Town bulletin).

Smithers permit questions

Where do I submit a building permit application in Smithers?

In person / email — Building Permit applications (hard copies) available at and submitted to the Town Office, 1027 Aldous Street. No online e-permitting portal noted.

Who issues electrical and gas permits in Smithers?

Technical Safety BC — electrical and gas permits are not issued by the Town; they are handled provincially by Technical Safety BC (the page does not administer them). Confirm directly with TSBC.

How much does a building permit cost in Smithers?

$80 application fee plus construction-value fee: $6.25 per $1,000 of value up to $1,000,000, then $5.50 per $1,000 above $1,000,000. Building inspector estimates value from submitted plans. Fees vary by project, so confirm the current schedule with Town of Smithers before budgeting.

What do I need to apply for a building permit in Smithers?

Town of Smithers asks for: Building Permit application form + $80 application fee; Site Plan (2 copies) showing lot shape/size, driveway, existing buildings, setbacks, project location; Building plans (2 copies): elevations, floor plans, cross sections; Site Disclosure Statement; Layout and certificates for engineered components (trusses, joists, beams); Home Owner Protection Office (BC Housing / home warranty) approval for new residences; Owner's Authorization Form (Appendix D) and Owner's Undertaking (Appendix E); Letters of Assurance from a Registered Professional (for engineered/complex work); Confirmation of Insurance (Appendix F) and required documentation for major occupancies (Appendix G).

Anything else to know about permits in Smithers?

Most permits issued within 20 working days depending on complexity/completeness. No permit needed for non-structural work (painting, same-size window/door swaps, fences, private sidewalks, non-structural re-roof/re-side). 2025 BC Building Code requirements apply (see Town bulletin).

Sources

General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with Town of Smithers before you build.