How to get a building permit in Richmond, BC

Where to apply, what Richmond asks for, what it costs, and who issues electrical and gas permits — with links to the city's own forms.

Where to apply in Richmond

MyPermit portal — https://www.richmond.ca/business-development/e-plan/mypermit.htm (accessed via a MyRichmond account). Self-guided step-by-step navigation, dynamic forms that show only relevant requirements, save-for-later, and online payment of eligible fees; 24/7 access. A mobile app is also available. Applications can alternatively be submitted in person at the Permits Counter in Richmond City Hall.

Official City of Richmond permit page

Building Approvals / Permits: phone 604-276-4118; email building@richmond.ca; Permits Counter, Richmond City Hall, 6911 No. 3 Road, Richmond BC.

Who issues electrical and gas permits

MIXED: Richmond does NOT run its own electrical program — 'The BC Safety Authority is the electrical permitting authority for Richmond,' so ELECTRICAL permits go to Technical Safety BC (get the electrical permit through TSBC before work starts). However Richmond DOES issue its own PLUMBING and GAS permits (and fire sprinkler permits) through the City building department. So: electrical = Technical Safety BC; gas = City of Richmond; plumbing = City of Richmond.

electrical
Technical Safety BC
gas
City of Richmond

Step by step in Richmond

  1. 1

    Confirm zoning before anything else

    Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — Richmond won't issue until land use is settled.

  2. 2

    Work out which permits you need

    Structural work needs a building permit from City of Richmond. Electrical and gas are separate and are issued by MIXED: Richmond does NOT run its own electrical program — 'The BC Safety Authority is the electrical permitting authority for Richmond,' so ELECTRICAL permits go to Technical Safety BC (get the electrical permit through TSBC before work starts). Plumbing is usually part of the building permit.

  3. 3

    Prepare drawings and documents

    City of Richmond asks for: Application via MyPermit portal (or in person at the Permits Counter); Correct application form by project type (see key forms); Construction drawings and site/plot plan; BC Energy Step Code compliance documentation for new construction; Letters of Assurance / registered professional (Schedule A/B/C) for engineered/complex work and geotechnical; Geotechnical report where applicable; Home warranty insurance for new homes (Homeowner Protection Act), or owner-builder exemption; Owner authorization where the applicant is not the owner; Separate Technical Safety BC electrical permit obtained before electrical work begins.

  4. 4

    Submit your application

    MyPermit portal — https://www.richmond.ca/business-development/e-plan/mypermit.htm (accessed via a MyRichmond account). Self-guided step-by-step navigation, dynamic forms that show only relevant requirements, save-for-later, and online payment of eligible fees; 24/7 access. A mobile app is also available. Applications can alternatively be submitted in person at the Permits Counter in Richmond City Hall.

  5. 5

    Pay the permit fee

    Building fees are set by City Bylaw — Consolidated Fees Bylaw 8636 (2011), Chapter 5 Finance & Budgets (see the Building fees pages of that bylaw). Fees are based on construction value; plumbing, gas and sprinkler permits have their own fee lines. (Confirm current amounts against the consolidated fees bylaw.) Confirm the current schedule with Richmond before you budget.

  6. 6

    Plan review, then build to inspections

    The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.

What Richmond asks for

  • Application via MyPermit portal (or in person at the Permits Counter)
  • Correct application form by project type (see key forms)
  • Construction drawings and site/plot plan
  • BC Energy Step Code compliance documentation for new construction
  • Letters of Assurance / registered professional (Schedule A/B/C) for engineered/complex work and geotechnical
  • Geotechnical report where applicable
  • Home warranty insurance for new homes (Homeowner Protection Act), or owner-builder exemption
  • Owner authorization where the applicant is not the owner
  • Separate Technical Safety BC electrical permit obtained before electrical work begins

Permit fees in Richmond

Building fees are set by City Bylaw — Consolidated Fees Bylaw 8636 (2011), Chapter 5 Finance & Budgets (see the Building fees pages of that bylaw). Fees are based on construction value; plumbing, gas and sprinkler permits have their own fee lines. (Confirm current amounts against the consolidated fees bylaw.)

Fees change and vary by project — confirm the current schedule with City of Richmond.

Richmond permit forms

Open a form here and fill it in without leaving the page.

Pick a form to open it here.

Worth knowing about Richmond

Electrical is the key difference vs Surrey/Burnaby/Vancouver — Richmond leaves electrical to Technical Safety BC while running its own gas and plumbing programs. Development permit may be required first for new/multi-unit builds. SSMUH-specific building permit form (PL-62) reflects BC's small-scale multi-unit housing rules. Email building@richmond.ca for building-permit questions.

Richmond permit questions

Where do I submit a building permit application in Richmond?

MyPermit portal — https://www.richmond.ca/business-development/e-plan/mypermit.htm (accessed via a MyRichmond account). Self-guided step-by-step navigation, dynamic forms that show only relevant requirements, save-for-later, and online payment of eligible fees; 24/7 access. A mobile app is also available. Applications can alternatively be submitted in person at the Permits Counter in Richmond City Hall.

Who issues electrical and gas permits in Richmond?

MIXED: Richmond does NOT run its own electrical program — 'The BC Safety Authority is the electrical permitting authority for Richmond,' so ELECTRICAL permits go to Technical Safety BC (get the electrical permit through TSBC before work starts). However Richmond DOES issue its own PLUMBING and GAS permits (and fire sprinkler permits) through the City building department. So: electrical = Technical Safety BC; gas = City of Richmond; plumbing = City of Richmond.

How much does a building permit cost in Richmond?

Building fees are set by City Bylaw — Consolidated Fees Bylaw 8636 (2011), Chapter 5 Finance & Budgets (see the Building fees pages of that bylaw). Fees are based on construction value; plumbing, gas and sprinkler permits have their own fee lines. (Confirm current amounts against the consolidated fees bylaw.) Fees vary by project, so confirm the current schedule with City of Richmond before budgeting.

What do I need to apply for a building permit in Richmond?

City of Richmond asks for: Application via MyPermit portal (or in person at the Permits Counter); Correct application form by project type (see key forms); Construction drawings and site/plot plan; BC Energy Step Code compliance documentation for new construction; Letters of Assurance / registered professional (Schedule A/B/C) for engineered/complex work and geotechnical; Geotechnical report where applicable; Home warranty insurance for new homes (Homeowner Protection Act), or owner-builder exemption; Owner authorization where the applicant is not the owner; Separate Technical Safety BC electrical permit obtained before electrical work begins.

Anything else to know about permits in Richmond?

Electrical is the key difference vs Surrey/Burnaby/Vancouver — Richmond leaves electrical to Technical Safety BC while running its own gas and plumbing programs. Development permit may be required first for new/multi-unit builds. SSMUH-specific building permit form (PL-62) reflects BC's small-scale multi-unit housing rules. Email building@richmond.ca for building-permit questions.

Sources

General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with City of Richmond before you build.