District of North Vancouver
How to get a building permit in District of North Vancouver, BC
Where to apply, what District of North Vancouver asks for, what it costs, and who issues electrical and gas permits — with links to the city's own forms.
Where to apply in District of North Vancouver
Email intake to building@dnv.org (no self-serve online building-permit portal). Trades permits (electrical, gas, plumbing, heating) use dedicated online application forms at dnv.org/page/electrical-permit-application-form etc. Payment link emailed after review; account portal is MyDNV. Permit lookup: dnv.org/page/look-up-a-permit.
Official District of North Vancouver permit pageDevelopment Services / Building Department: building@dnv.org; District Hall, 355 West Queens Road, North Vancouver, BC V7N 4N5; 604-990-2311
Who issues electrical and gas permits
The District of North Vancouver runs its OWN electrical AND gas permit and inspection programs (NOT Technical Safety BC). DNV issues electrical permits (with its own DNV electrical inspector) and gas permits directly via online application forms, and applies its own homeowner-permit rules. This is a delegated municipality that took over gas/electrical inspection.
- electrical
- District of North Vancouver
- gas
- District of North Vancouver
Step by step in District of North Vancouver
- 1
Confirm zoning before anything else
Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — District of North Vancouver won't issue until land use is settled.
- 2
Work out which permits you need
Structural work needs a building permit from District of North Vancouver. Electrical and gas are separate and are issued by The District of North Vancouver runs its OWN electrical AND gas permit and inspection programs (NOT Technical Safety BC). Plumbing is usually part of the building permit.
- 3
Prepare drawings and documents
District of North Vancouver asks for: Electronic submission only; contact building@dnv.org to arrange a building-permit intake; Building Permit Application Form (required for all applications); Building Requirements Questionnaire (required for all applications); Project-specific application checklist (New Construction SF, Renovation/Addition & Deck, Interior Renovation & Secondary Suite, Coach House, Swimming Pool/Accessory, Retaining Walls, Photovoltaic Solar); GEN 101 Authorization to Represent Owner form (if agent applying); Site plan and survey forms graded Simple/Moderate/Complex (BLD 106/107/108 site plan; BLD 103/104/105 survey); BLD 101 Letter of Assurance and Schedule-style forms; professional (AIBC/EGBC) sealed drawings for complex work; architect required where Architects Regulation applies (e.g. mezzanine additions); Documents must be named per the District's building permit submission instructions or they are rejected; WorkSafeBC hazmat clearance certificate required for alterations to buildings built before 1990 before any inspection; Development permit generally required BEFORE building permit if property is in a Development Permit Area (DPA); Slope/geotech reports for sloping sites (SPE 104 >10 deg, SPE 105 >20 deg), flood (SPE 106), creek (SPE 107), wildfire (SPE 115), stormwater/geotech (SPE 112); Trades permits (electrical, mechanical, plumbing, gas) applied for AFTER the building permit is issued; Start work within 6 months of permit; complete within 2 years.
- 4
Submit your application
Email intake to building@dnv.org (no self-serve online building-permit portal). Trades permits (electrical, gas, plumbing, heating) use dedicated online application forms at dnv.org/page/electrical-permit-application-form etc. Payment link emailed after review; account portal is MyDNV. Permit lookup: dnv.org/page/look-up-a-permit.
- 5
Pay the permit fee
50% non-refundable estimated permit fee paid at application; remaining balance, securities and charges paid before permit issuance. Fees set by the DNV Fees and Charges Bylaw (gas permits calculated by fixture; construction-value based for building). New-construction single-family permits take approx. 12-16 weeks. Confirm the current schedule with District of North Vancouver before you budget.
- 6
Plan review, then build to inspections
The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.
What District of North Vancouver asks for
- Electronic submission only; contact building@dnv.org to arrange a building-permit intake
- Building Permit Application Form (required for all applications)
- Building Requirements Questionnaire (required for all applications)
- Project-specific application checklist (New Construction SF, Renovation/Addition & Deck, Interior Renovation & Secondary Suite, Coach House, Swimming Pool/Accessory, Retaining Walls, Photovoltaic Solar)
- GEN 101 Authorization to Represent Owner form (if agent applying)
- Site plan and survey forms graded Simple/Moderate/Complex (BLD 106/107/108 site plan; BLD 103/104/105 survey)
- BLD 101 Letter of Assurance and Schedule-style forms; professional (AIBC/EGBC) sealed drawings for complex work; architect required where Architects Regulation applies (e.g. mezzanine additions)
- Documents must be named per the District's building permit submission instructions or they are rejected
- WorkSafeBC hazmat clearance certificate required for alterations to buildings built before 1990 before any inspection
- Development permit generally required BEFORE building permit if property is in a Development Permit Area (DPA)
- Slope/geotech reports for sloping sites (SPE 104 >10 deg, SPE 105 >20 deg), flood (SPE 106), creek (SPE 107), wildfire (SPE 115), stormwater/geotech (SPE 112)
- Trades permits (electrical, mechanical, plumbing, gas) applied for AFTER the building permit is issued
- Start work within 6 months of permit; complete within 2 years
Permit fees in District of North Vancouver
50% non-refundable estimated permit fee paid at application; remaining balance, securities and charges paid before permit issuance. Fees set by the DNV Fees and Charges Bylaw (gas permits calculated by fixture; construction-value based for building). New-construction single-family permits take approx. 12-16 weeks.
Fees change and vary by project — confirm the current schedule with District of North Vancouver.
District of North Vancouver permit forms
Open a form here and fill it in without leaving the page.
Pick a form to open it here.
Permit types in District of North Vancouver
Electrical permit
A safety permit required before doing regulated electrical work in BC — an Installation Permit for a defined project (new wiring, upgrades, alterations), or an Operating Permit for ongoing maintenance of existing electrical equipment in larger/commercial facilities.
Gas permit
A safety permit required before installing or altering regulated gas equipment/systems in BC (natural gas, LPG/propane, hydrogen, digester/landfill gas, etc.) — a Gas Installation Permit for the work itself, plus mandatory inspection notification after each phase.
Plumbing permit
A trade permit (often issued separately from, or alongside, the building permit) authorizing installation, extension, or alteration of potable water, drainage-waste-vent, and connections to municipal water/sewer, verified against the BC Plumbing Code.
Demolition permit
A municipal permit to tear down or remove a building or structure, conditional on safe utility disconnections, a pre-demolition hazardous-materials (asbestos) survey and abatement, and — in many cities — recycling/deconstruction requirements backed by a refundable deposit.
Worth knowing about District of North Vancouver
Homeowners can only self-apply for electrical/gas permits on detached single-family homes they occupy with no secondary suite/rental. Development-permit-first in DPAs. Extensive hazard forms for sloping/creek/flood/wildfire sites. Demolition subject to Demolition Waste Reduction Bylaw. Contractors need a valid DNV business licence + trades qualification certificate.
District of North Vancouver permit questions
Where do I submit a building permit application in District of North Vancouver?
Email intake to building@dnv.org (no self-serve online building-permit portal). Trades permits (electrical, gas, plumbing, heating) use dedicated online application forms at dnv.org/page/electrical-permit-application-form etc. Payment link emailed after review; account portal is MyDNV. Permit lookup: dnv.org/page/look-up-a-permit.
Who issues electrical and gas permits in District of North Vancouver?
The District of North Vancouver runs its OWN electrical AND gas permit and inspection programs (NOT Technical Safety BC). DNV issues electrical permits (with its own DNV electrical inspector) and gas permits directly via online application forms, and applies its own homeowner-permit rules. This is a delegated municipality that took over gas/electrical inspection.
How much does a building permit cost in District of North Vancouver?
50% non-refundable estimated permit fee paid at application; remaining balance, securities and charges paid before permit issuance. Fees set by the DNV Fees and Charges Bylaw (gas permits calculated by fixture; construction-value based for building). New-construction single-family permits take approx. 12-16 weeks. Fees vary by project, so confirm the current schedule with District of North Vancouver before budgeting.
What do I need to apply for a building permit in District of North Vancouver?
District of North Vancouver asks for: Electronic submission only; contact building@dnv.org to arrange a building-permit intake; Building Permit Application Form (required for all applications); Building Requirements Questionnaire (required for all applications); Project-specific application checklist (New Construction SF, Renovation/Addition & Deck, Interior Renovation & Secondary Suite, Coach House, Swimming Pool/Accessory, Retaining Walls, Photovoltaic Solar); GEN 101 Authorization to Represent Owner form (if agent applying); Site plan and survey forms graded Simple/Moderate/Complex (BLD 106/107/108 site plan; BLD 103/104/105 survey); BLD 101 Letter of Assurance and Schedule-style forms; professional (AIBC/EGBC) sealed drawings for complex work; architect required where Architects Regulation applies (e.g. mezzanine additions); Documents must be named per the District's building permit submission instructions or they are rejected; WorkSafeBC hazmat clearance certificate required for alterations to buildings built before 1990 before any inspection; Development permit generally required BEFORE building permit if property is in a Development Permit Area (DPA); Slope/geotech reports for sloping sites (SPE 104 >10 deg, SPE 105 >20 deg), flood (SPE 106), creek (SPE 107), wildfire (SPE 115), stormwater/geotech (SPE 112); Trades permits (electrical, mechanical, plumbing, gas) applied for AFTER the building permit is issued; Start work within 6 months of permit; complete within 2 years.
Anything else to know about permits in District of North Vancouver?
Homeowners can only self-apply for electrical/gas permits on detached single-family homes they occupy with no secondary suite/rental. Development-permit-first in DPAs. Extensive hazard forms for sloping/creek/flood/wildfire sites. Demolition subject to Demolition Waste Reduction Bylaw. Contractors need a valid DNV business licence + trades qualification certificate.
Sources
- https://www.dnv.org/business-development/building-permit-single-family-home
- https://www.dnv.org/business-development/building-permit-commercial-and-multi-family-home
- https://www.dnv.org/business-development/electrical-permit
- https://www.dnv.org/business-development/gas-permit
- https://docs.dnv.org/documents/building-permit-submission-instructions.pdf
General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with District of North Vancouver before you build.