Village of New Denver

How to get a building permit in New Denver, BC

Where to apply, what New Denver asks for, what it costs, and who issues electrical and gas permits — with links to the city's own forms.

Where to apply in New Denver

In person / email — NO online portal. Building permits are administered by the Regional District of Central Kootenay (RDCK) Building Service. Applications submitted as PDF to buildingdepartment@rdck.bc.ca, or forms downloaded/picked up at RDCK offices. Village Office confirms zoning/OCP compliance first.

Official Village of New Denver permit page

Village of New Denver Office, 115 Slocan Ave (PO Box 40), New Denver BC V0G 1S0, 250-358-2316, office@newdenver.ca. Building permits handled by RDCK Nakusp office: 250-265-4111, nakuspbuilding@rdck.bc.ca (RDCK head office Nelson 250-352-8155, buildingdepartment@rdck.bc.ca).

Who issues electrical and gas permits

Technical Safety BC (issues all electrical and gas permits/inspections; not the Village or RDCK)

electrical
Technical Safety BC
Sending this to Village of New Denver instead won't get forwarded — it starts over. On a service upgrade that also pushes out your BC Hydro reconnect, usually the longest lead time on the whole job.
gas
Technical Safety BC
Sending this to Village of New Denver instead won't get forwarded — it starts over, and gas work can't be inspected or turned on until the right authority has issued the permit.

Step by step in New Denver

  1. 1

    Confirm zoning before anything else

    Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — New Denver won't issue until land use is settled.

  2. 2

    Work out which permits you need

    Structural work needs a building permit from Village of New Denver. Electrical and gas are separate and are issued by Technical Safety BC (issues all electrical and gas permits/inspections; not the Village or RDCK). Plumbing is usually part of the building permit.

  3. 3

    Prepare drawings and documents

    Village of New Denver asks for: Any structure over 10 m2 (approx. 107-108 sq ft) requires a permit; Completed RDCK Building Permit Application Form (fillable PDF); Project-specific RDCK checklist (Single Family Dwelling, Accessory Building, Plumbing, Demolition, etc.); Design/construction drawings and plans; Site plan showing location relative to property lines; Construction, Demolition & Renovation Waste Declaration Form; Owner authorization / Owner's Representative sign-off; BC Housing new-home registration (Home Owner Protection) required for new dwellings; BC Energy Step Code compliance for new residential construction; WorkSafeBC / asbestos clearance where demolition or renovation applies; Village Office reviews for Zoning Bylaw No. 612, 2007 and Building Bylaw No. 595/670 compliance before RDCK plan review.

  4. 4

    Submit your application

    In person / email — NO online portal. Building permits are administered by the Regional District of Central Kootenay (RDCK) Building Service. Applications submitted as PDF to buildingdepartment@rdck.bc.ca, or forms downloaded/picked up at RDCK offices. Village Office confirms zoning/OCP compliance first.

  5. 5

    Pay the permit fee

    Plan-check deposit fee per Schedule A, RDCK Building Bylaw No. 2200, 2010 (SFD $100; multi-family/commercial/industrial/institutional $200; accessory building/addition $50); full permit fees per RDCK Fee Schedule Bylaw No. 2383-2014, value-of-construction based. Confirm the current schedule with New Denver before you budget.

  6. 6

    Plan review, then build to inspections

    The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.

What New Denver asks for

  • Any structure over 10 m2 (approx. 107-108 sq ft) requires a permit
  • Completed RDCK Building Permit Application Form (fillable PDF)
  • Project-specific RDCK checklist (Single Family Dwelling, Accessory Building, Plumbing, Demolition, etc.)
  • Design/construction drawings and plans
  • Site plan showing location relative to property lines
  • Construction, Demolition & Renovation Waste Declaration Form
  • Owner authorization / Owner's Representative sign-off
  • BC Housing new-home registration (Home Owner Protection) required for new dwellings
  • BC Energy Step Code compliance for new residential construction
  • WorkSafeBC / asbestos clearance where demolition or renovation applies
  • Village Office reviews for Zoning Bylaw No. 612, 2007 and Building Bylaw No. 595/670 compliance before RDCK plan review

Permit fees in New Denver

Plan-check deposit fee per Schedule A, RDCK Building Bylaw No. 2200, 2010 (SFD $100; multi-family/commercial/industrial/institutional $200; accessory building/addition $50); full permit fees per RDCK Fee Schedule Bylaw No. 2383-2014, value-of-construction based.

Fees change and vary by project — confirm the current schedule with Village of New Denver.

Worth knowing about New Denver

New Denver does NOT run its own building department — building permits, plan review, and inspections are delegated to the RDCK Building Service (Nakusp office serves New Denver, Silverton, Slocan). The Village handles zoning/OCP referral only. Electrical and gas go to Technical Safety BC.

New Denver permit questions

Where do I submit a building permit application in New Denver?

In person / email — NO online portal. Building permits are administered by the Regional District of Central Kootenay (RDCK) Building Service. Applications submitted as PDF to buildingdepartment@rdck.bc.ca, or forms downloaded/picked up at RDCK offices. Village Office confirms zoning/OCP compliance first.

Who issues electrical and gas permits in New Denver?

Technical Safety BC (issues all electrical and gas permits/inspections; not the Village or RDCK)

How much does a building permit cost in New Denver?

Plan-check deposit fee per Schedule A, RDCK Building Bylaw No. 2200, 2010 (SFD $100; multi-family/commercial/industrial/institutional $200; accessory building/addition $50); full permit fees per RDCK Fee Schedule Bylaw No. 2383-2014, value-of-construction based. Fees vary by project, so confirm the current schedule with Village of New Denver before budgeting.

What do I need to apply for a building permit in New Denver?

Village of New Denver asks for: Any structure over 10 m2 (approx. 107-108 sq ft) requires a permit; Completed RDCK Building Permit Application Form (fillable PDF); Project-specific RDCK checklist (Single Family Dwelling, Accessory Building, Plumbing, Demolition, etc.); Design/construction drawings and plans; Site plan showing location relative to property lines; Construction, Demolition & Renovation Waste Declaration Form; Owner authorization / Owner's Representative sign-off; BC Housing new-home registration (Home Owner Protection) required for new dwellings; BC Energy Step Code compliance for new residential construction; WorkSafeBC / asbestos clearance where demolition or renovation applies; Village Office reviews for Zoning Bylaw No. 612, 2007 and Building Bylaw No. 595/670 compliance before RDCK plan review.

Anything else to know about permits in New Denver?

New Denver does NOT run its own building department — building permits, plan review, and inspections are delegated to the RDCK Building Service (Nakusp office serves New Denver, Silverton, Slocan). The Village handles zoning/OCP referral only. Electrical and gas go to Technical Safety BC.

Sources

General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with Village of New Denver before you build.