How to get a building permit in Delta, BC

Where to apply, what Delta asks for, what it costs, and who issues electrical and gas permits — with links to the city's own forms.

Where to apply in Delta

TWO online portals, mandatory two-step process (paper/email applications no longer accepted): (1) 'Delta Online' eApply/Prospero — https://deltaonline.ca (complete the application form + pay the application fee); (2) 'ePlan' portal — upload required drawings then click 'Submit for Review'. Application is only reviewed once BOTH steps are complete. Inspections booked via 'eInspections' (up to 5 days ahead) on deltaonline.ca.

Official Corporation of Delta (City of Delta) permit page

Application Centre / Development Department: 604-946-3380; development@delta.ca. Portal: deltaonline.ca.

Who issues electrical and gas permits

Technical Safety BC — Delta states administration of safety standards for electrical, gas, boiler and other technical equipment is delegated to Technical Safety BC. Contractors apply to TSBC for electrical/gas; at FRAMING inspection Delta requires documentation confirming those TSBC permits were issued. (Delta itself issues plumbing permits.)

electrical
Technical Safety BC
gas
Technical Safety BC

Step by step in Delta

  1. 1

    Confirm zoning before anything else

    Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — Delta won't issue until land use is settled.

  2. 2

    Work out which permits you need

    Structural work needs a building permit from Corporation of Delta (City of Delta). Electrical and gas are separate and are issued by Technical Safety BC — Delta states administration of safety standards for electrical, gas, boiler and other technical equipment is delegated to Technical Safety BC. Plumbing is usually part of the building permit.

  3. 3

    Prepare drawings and documents

    Corporation of Delta (City of Delta) asks for: Two-step online submission: Delta Online application + fee, then ePlan drawing upload (submissions must be digital; registered-professional seals in digital format with verification embedded in the documents); Drawings scaled to scope (site plan, floor plans, elevations, sections); requirements 'dependent on the scope and nature of the proposal'; Site plan with existing/proposed buildings and setbacks; BC Energy Step Code: Part 9 homes must meet STEP 3; all new/substantially-reconstructed dwellings require energy modelling by a certified Energy Advisor with the application, and an As-Built Step Code compliance report at Final/Occupancy; New-home warranty: enrol with BC Housing or qualify for an exemption before starting a new home; Owner authorization / Letter of Authorization for Strata Properties where applicable; Registered professional Letters of Assurance (Schedule B) for complex/engineered work; Geotechnical report for hillside / slope-instability development permit areas; engineered SEAWALL (structural engineer) for Boundary Bay shorefront properties; Contaminated Site Profile and Fraser Health approvals where triggered; Electrical & gas permits from Technical Safety BC (proof required at framing inspection).

  4. 4

    Submit your application

    TWO online portals, mandatory two-step process (paper/email applications no longer accepted): (1) 'Delta Online' eApply/Prospero — https://deltaonline.ca (complete the application form + pay the application fee); (2) 'ePlan' portal — upload required drawings then click 'Submit for Review'. Application is only reviewed once BOTH steps are complete. Inspections booked via 'eInspections' (up to 5 days ahead) on deltaonline.ca.

  5. 5

    Pay the permit fee

    Varies by permit type/scope; fee-payment request and instructions sent after the application is received. Building permit = plan-processing fee + building permit fee (scales with construction value). Plumbing fees calculated by number of fixtures and whether fire-sprinkler/hydrant/hot-water-heating systems are involved. Demolition permit approx. flat fee (~$153). Confirm the current schedule with Delta before you budget.

  6. 6

    Plan review, then build to inspections

    The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.

What Delta asks for

  • Two-step online submission: Delta Online application + fee, then ePlan drawing upload (submissions must be digital; registered-professional seals in digital format with verification embedded in the documents)
  • Drawings scaled to scope (site plan, floor plans, elevations, sections); requirements 'dependent on the scope and nature of the proposal'
  • Site plan with existing/proposed buildings and setbacks
  • BC Energy Step Code: Part 9 homes must meet STEP 3; all new/substantially-reconstructed dwellings require energy modelling by a certified Energy Advisor with the application, and an As-Built Step Code compliance report at Final/Occupancy
  • New-home warranty: enrol with BC Housing or qualify for an exemption before starting a new home
  • Owner authorization / Letter of Authorization for Strata Properties where applicable
  • Registered professional Letters of Assurance (Schedule B) for complex/engineered work
  • Geotechnical report for hillside / slope-instability development permit areas; engineered SEAWALL (structural engineer) for Boundary Bay shorefront properties
  • Contaminated Site Profile and Fraser Health approvals where triggered
  • Electrical & gas permits from Technical Safety BC (proof required at framing inspection)

Permit fees in Delta

Varies by permit type/scope; fee-payment request and instructions sent after the application is received. Building permit = plan-processing fee + building permit fee (scales with construction value). Plumbing fees calculated by number of fixtures and whether fire-sprinkler/hydrant/hot-water-heating systems are involved. Demolition permit approx. flat fee (~$153).

Fees change and vary by project — confirm the current schedule with Corporation of Delta (City of Delta).

Delta permit forms

Open a form here and fill it in without leaving the page.

Pick a form to open it here.

Permit types in Delta

Plumbing permit

A trade permit (often issued separately from, or alongside, the building permit) authorizing installation, extension, or alteration of potable water, drainage-waste-vent, and connections to municipal water/sewer, verified against the BC Plumbing Code.

Worth knowing about Delta

Fully digital, two-portal workflow (Delta Online + ePlan) — no paper/email. GEOTECHNICAL requirements for designated slope-instability development permit areas and engineered SEAWALL requirements for Boundary Bay shorefront are Delta-specific. Step Code Step 3 mandatory for Part 9 with mandatory Energy Advisor modelling. Development Permit may be required before building permit. Contaminated Site Profile / Fraser Health approvals can be triggers.

Delta permit questions

Where do I submit a building permit application in Delta?

TWO online portals, mandatory two-step process (paper/email applications no longer accepted): (1) 'Delta Online' eApply/Prospero — https://deltaonline.ca (complete the application form + pay the application fee); (2) 'ePlan' portal — upload required drawings then click 'Submit for Review'. Application is only reviewed once BOTH steps are complete. Inspections booked via 'eInspections' (up to 5 days ahead) on deltaonline.ca.

Who issues electrical and gas permits in Delta?

Technical Safety BC — Delta states administration of safety standards for electrical, gas, boiler and other technical equipment is delegated to Technical Safety BC. Contractors apply to TSBC for electrical/gas; at FRAMING inspection Delta requires documentation confirming those TSBC permits were issued. (Delta itself issues plumbing permits.)

How much does a building permit cost in Delta?

Varies by permit type/scope; fee-payment request and instructions sent after the application is received. Building permit = plan-processing fee + building permit fee (scales with construction value). Plumbing fees calculated by number of fixtures and whether fire-sprinkler/hydrant/hot-water-heating systems are involved. Demolition permit approx. flat fee (~$153). Fees vary by project, so confirm the current schedule with Corporation of Delta (City of Delta) before budgeting.

What do I need to apply for a building permit in Delta?

Corporation of Delta (City of Delta) asks for: Two-step online submission: Delta Online application + fee, then ePlan drawing upload (submissions must be digital; registered-professional seals in digital format with verification embedded in the documents); Drawings scaled to scope (site plan, floor plans, elevations, sections); requirements 'dependent on the scope and nature of the proposal'; Site plan with existing/proposed buildings and setbacks; BC Energy Step Code: Part 9 homes must meet STEP 3; all new/substantially-reconstructed dwellings require energy modelling by a certified Energy Advisor with the application, and an As-Built Step Code compliance report at Final/Occupancy; New-home warranty: enrol with BC Housing or qualify for an exemption before starting a new home; Owner authorization / Letter of Authorization for Strata Properties where applicable; Registered professional Letters of Assurance (Schedule B) for complex/engineered work; Geotechnical report for hillside / slope-instability development permit areas; engineered SEAWALL (structural engineer) for Boundary Bay shorefront properties; Contaminated Site Profile and Fraser Health approvals where triggered; Electrical & gas permits from Technical Safety BC (proof required at framing inspection).

Anything else to know about permits in Delta?

Fully digital, two-portal workflow (Delta Online + ePlan) — no paper/email. GEOTECHNICAL requirements for designated slope-instability development permit areas and engineered SEAWALL requirements for Boundary Bay shorefront are Delta-specific. Step Code Step 3 mandatory for Part 9 with mandatory Energy Advisor modelling. Development Permit may be required before building permit. Contaminated Site Profile / Fraser Health approvals can be triggers.

Sources

General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with Corporation of Delta (City of Delta) before you build.