Town of Creston

How to get a building permit in Creston, BC

Where to apply, what Creston asks for, what it costs, and who issues electrical and gas permits — with links to the city's own forms.

Where to apply in Creston

In person / email — no online permitting portal. Drawings submitted as two paper sets plus a digital copy emailed to building@creston.ca; large-format plans (over 11x17) must be provided as hard copies dropped at Town Hall. (No Cloudpermit/ProjectDox.)

Official Town of Creston permit page

Town of Creston Building Department, 238 10th Ave N, PO Box 1339, Creston BC V0B 1G0 — phone 250-428-2214 ext. 431, fax 250-428-9164, email building@creston.ca. Manager of Building & Bylaw Services: Brandon Vigne (Brandon.Vigne@creston.ca).

Who issues electrical and gas permits

Technical Safety BC — electrical and gas installation permits are handled provincially by TSBC, not by the Town (BC standard; the Town issues building & plumbing only).

electrical
Technical Safety BC
Sending this to Town of Creston instead won't get forwarded — it starts over. On a service upgrade that also pushes out your BC Hydro reconnect, usually the longest lead time on the whole job.
gas
Technical Safety BC
Sending this to Town of Creston instead won't get forwarded — it starts over, and gas work can't be inspected or turned on until the right authority has issued the permit.

Step by step in Creston

  1. 1

    Confirm zoning before anything else

    Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — Creston won't issue until land use is settled.

  2. 2

    Work out which permits you need

    Structural work needs a building permit from Town of Creston. Electrical and gas are separate and are issued by Technical Safety BC — electrical and gas installation permits are handled provincially by TSBC, not by the Town (BC standard; the Town issues building & plumbing only). Plumbing is usually part of the building permit.

  3. 3

    Prepare drawings and documents

    Town of Creston asks for: Two sets of scaled drawings + one digital copy emailed to building@creston.ca; Sealed engineer's drawings + Schedule B where applicable; engineered truss & beam layouts (note solar-panel locations on truss layouts); Owner authorization if applicant is not the owner; BC Energy Step Code Pre-Construction Compliance Report for all new commercial & residential construction (Step Code adopted by reference in Building Bylaw 1394); HPO / BC Housing New Home Registration for new residential construction (home warranty); Current State of Title (within 30 days) with any covenants, easements, rights-of-way; Detailed site plan (lot area/dimensions, foundation outline, setbacks, driveway, septic, easements, retaining walls); Retaining walls over 1.2 m require a separate permit; Commercial/Part 3: sealed architectural & engineering drawings, sealed Building Code Analysis, Construction Fire Safety Plan, Interior Health approval (food/pool/salon), Site Disclosure Statement; WorkSafeBC asbestos/hazmat pre-work inspection for pre-1990 buildings (recommended per OHS).

  4. 4

    Submit your application

    In person / email — no online permitting portal. Drawings submitted as two paper sets plus a digital copy emailed to building@creston.ca; large-format plans (over 11x17) must be provided as hard copies dropped at Town Hall. (No Cloudpermit/ProjectDox.)

  5. 5

    Pay the permit fee

    Fees set by the Town's Fees and Charges Bylaw (referenced in Building Bylaw 1394), based on value/estimated cost of construction. Permit fee reduced 10% (max $300) where professional certification/Letters of Assurance replace the plan-checking otherwise done by the Building Inspector. Confirm the current schedule with Creston before you budget.

  6. 6

    Plan review, then build to inspections

    The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.

What Creston asks for

  • Two sets of scaled drawings + one digital copy emailed to building@creston.ca
  • Sealed engineer's drawings + Schedule B where applicable; engineered truss & beam layouts (note solar-panel locations on truss layouts)
  • Owner authorization if applicant is not the owner
  • BC Energy Step Code Pre-Construction Compliance Report for all new commercial & residential construction (Step Code adopted by reference in Building Bylaw 1394)
  • HPO / BC Housing New Home Registration for new residential construction (home warranty)
  • Current State of Title (within 30 days) with any covenants, easements, rights-of-way
  • Detailed site plan (lot area/dimensions, foundation outline, setbacks, driveway, septic, easements, retaining walls)
  • Retaining walls over 1.2 m require a separate permit
  • Commercial/Part 3: sealed architectural & engineering drawings, sealed Building Code Analysis, Construction Fire Safety Plan, Interior Health approval (food/pool/salon), Site Disclosure Statement
  • WorkSafeBC asbestos/hazmat pre-work inspection for pre-1990 buildings (recommended per OHS)

Permit fees in Creston

Fees set by the Town's Fees and Charges Bylaw (referenced in Building Bylaw 1394), based on value/estimated cost of construction. Permit fee reduced 10% (max $300) where professional certification/Letters of Assurance replace the plan-checking otherwise done by the Building Inspector.

Fees change and vary by project — confirm the current schedule with Town of Creston.

Worth knowing about Creston

Own building department — does not rely on RDCK/RDKB. BC Energy Step Code is formally adopted by reference in Building Bylaw No. 1394. Incomplete applications do not enter the review queue; building without a permit can trigger stop-work orders, fines, or a notice on title. Secondary suites need a separate Advisory #1 from the Building Official.

Creston permit questions

Where do I submit a building permit application in Creston?

In person / email — no online permitting portal. Drawings submitted as two paper sets plus a digital copy emailed to building@creston.ca; large-format plans (over 11x17) must be provided as hard copies dropped at Town Hall. (No Cloudpermit/ProjectDox.)

Who issues electrical and gas permits in Creston?

Technical Safety BC — electrical and gas installation permits are handled provincially by TSBC, not by the Town (BC standard; the Town issues building & plumbing only).

How much does a building permit cost in Creston?

Fees set by the Town's Fees and Charges Bylaw (referenced in Building Bylaw 1394), based on value/estimated cost of construction. Permit fee reduced 10% (max $300) where professional certification/Letters of Assurance replace the plan-checking otherwise done by the Building Inspector. Fees vary by project, so confirm the current schedule with Town of Creston before budgeting.

What do I need to apply for a building permit in Creston?

Town of Creston asks for: Two sets of scaled drawings + one digital copy emailed to building@creston.ca; Sealed engineer's drawings + Schedule B where applicable; engineered truss & beam layouts (note solar-panel locations on truss layouts); Owner authorization if applicant is not the owner; BC Energy Step Code Pre-Construction Compliance Report for all new commercial & residential construction (Step Code adopted by reference in Building Bylaw 1394); HPO / BC Housing New Home Registration for new residential construction (home warranty); Current State of Title (within 30 days) with any covenants, easements, rights-of-way; Detailed site plan (lot area/dimensions, foundation outline, setbacks, driveway, septic, easements, retaining walls); Retaining walls over 1.2 m require a separate permit; Commercial/Part 3: sealed architectural & engineering drawings, sealed Building Code Analysis, Construction Fire Safety Plan, Interior Health approval (food/pool/salon), Site Disclosure Statement; WorkSafeBC asbestos/hazmat pre-work inspection for pre-1990 buildings (recommended per OHS).

Anything else to know about permits in Creston?

Own building department — does not rely on RDCK/RDKB. BC Energy Step Code is formally adopted by reference in Building Bylaw No. 1394. Incomplete applications do not enter the review queue; building without a permit can trigger stop-work orders, fines, or a notice on title. Secondary suites need a separate Advisory #1 from the Building Official.

Sources

General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with Town of Creston before you build.