Where to apply in Comox

PSD Citywide Portal (https://citywideportal.com) — online only; create account, submit and track applications digitally

Official Town of Comox permit page

Development Services / Building Dept — 250-339-1118 (or Town Hall 250-339-2202), planning@comox.ca, 1809 Beaufort Ave, Comox BC V9M 1R9; Mon–Fri 8:30am–4:30pm

Who issues electrical and gas permits

Technical Safety BC (province-wide authority; Comox is not a delegated municipality)

electrical
Technical Safety BC
gas
Technical Safety BC

Step by step in Comox

  1. 1

    Confirm zoning before anything else

    Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — Comox won't issue until land use is settled.

  2. 2

    Work out which permits you need

    Structural work needs a building permit from Town of Comox. Electrical and gas are separate and are issued by Technical Safety BC (province-wide authority; Comox is not a delegated municipality). Plumbing is usually part of the building permit.

  3. 3

    Prepare drawings and documents

    Town of Comox asks for: Applications submitted online via PSD Citywide portal only (no counter/email intake); Documents required are listed per application type at time of submission in the portal; Must comply with BC Building Code 2024; BC Energy Step Code (Step Code) compliance required; Seismic bracing requirements; Radon rough-in requirements; Each permit reviewed by Engineering (servicing, driveway, off-site) and Planning (zoning, Development Permit Areas).

  4. 4

    Submit your application

    PSD Citywide Portal (https://citywideportal.com) — online only; create account, submit and track applications digitally

  5. 5

    Pay the permit fee

    Not published on the building page; fees set by Building Bylaw / fee schedule. Confirm with Development Services. Confirm the current schedule with Comox before you budget.

  6. 6

    Plan review, then build to inspections

    The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.

What Comox asks for

  • Applications submitted online via PSD Citywide portal only (no counter/email intake)
  • Documents required are listed per application type at time of submission in the portal
  • Must comply with BC Building Code 2024
  • BC Energy Step Code (Step Code) compliance required
  • Seismic bracing requirements
  • Radon rough-in requirements
  • Each permit reviewed by Engineering (servicing, driveway, off-site) and Planning (zoning, Development Permit Areas)

Permit fees in Comox

Not published on the building page; fees set by Building Bylaw / fee schedule. Confirm with Development Services.

Fees change and vary by project — confirm the current schedule with Town of Comox.

Permit types in Comox

Plumbing permit

A trade permit (often issued separately from, or alongside, the building permit) authorizing installation, extension, or alteration of potable water, drainage-waste-vent, and connections to municipal water/sewer, verified against the BC Plumbing Code.

Demolition permit

A municipal permit to tear down or remove a building or structure, conditional on safe utility disconnections, a pre-demolition hazardous-materials (asbestos) survey and abatement, and — in many cities — recycling/deconstruction requirements backed by a refundable deposit.

Worth knowing about Comox

Fully online intake through PSD Citywide. Typical processing 2–4 weeks when complete. Development Permit is a separate Planning approval that may be needed before a building permit. Uses BCBC 2024, seismic bracing and radon rough-in requirements.

Comox permit questions

Where do I submit a building permit application in Comox?

PSD Citywide Portal (https://citywideportal.com) — online only; create account, submit and track applications digitally

Who issues electrical and gas permits in Comox?

Technical Safety BC (province-wide authority; Comox is not a delegated municipality)

How much does a building permit cost in Comox?

Not published on the building page; fees set by Building Bylaw / fee schedule. Confirm with Development Services. Fees vary by project, so confirm the current schedule with Town of Comox before budgeting.

What do I need to apply for a building permit in Comox?

Town of Comox asks for: Applications submitted online via PSD Citywide portal only (no counter/email intake); Documents required are listed per application type at time of submission in the portal; Must comply with BC Building Code 2024; BC Energy Step Code (Step Code) compliance required; Seismic bracing requirements; Radon rough-in requirements; Each permit reviewed by Engineering (servicing, driveway, off-site) and Planning (zoning, Development Permit Areas).

Anything else to know about permits in Comox?

Fully online intake through PSD Citywide. Typical processing 2–4 weeks when complete. Development Permit is a separate Planning approval that may be needed before a building permit. Uses BCBC 2024, seismic bracing and radon rough-in requirements.

Sources

General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with Town of Comox before you build.

See what's being built in Comox

Construction Radar turns building-permit data into a live map of real construction jobs — who's building, what it's worth, and who to call.

Start for free