How to get a building permit in Chilliwack, BC

Where to apply, what Chilliwack asks for, what it costs, and who issues electrical and gas permits — with links to the city's own forms.

Where to apply in Chilliwack

MyCity Portal for online building permit applications, with ProjectDox used for drawing/document upload and review. Online submission accepted for Part 9 residential (new single/two-family, additions, renovations), rural/residential accessory, agricultural buildings, Part 3 tenant improvements, demolition, utility connection, and sign permits (pylon/fascia). New Part 3 buildings must be submitted as hard copies. Register first, then apply under Applications > Building Permit > Apply for a new permit. Online applications page: https://www.chilliwack.com/main/page.cfm?id=3198

Official City of Chilliwack permit page

Building Division, 8550 Young Rd, Chilliwack, BC V2P 8A4. Phone 604-793-2905 (Building Dept). Manager: Rob Goertzen.

Who issues electrical and gas permits

Technical Safety BC issues and inspects ELECTRICAL and GAS permits for Chilliwack. The City does NOT run its own electrical program. Apply directly to Technical Safety BC; homeowner electrical/gas permits limited to own principal residence (not suites/rentals).

electrical
Technical Safety BC
gas
Technical Safety BC

Step by step in Chilliwack

  1. 1

    Confirm zoning before anything else

    Check the property's zone, setbacks, height and lot coverage, and whether it sits in a Development Permit Area. If it does, that approval has to come before the building permit — Chilliwack won't issue until land use is settled.

  2. 2

    Work out which permits you need

    Structural work needs a building permit from City of Chilliwack. Electrical and gas are separate and are issued by Technical Safety BC issues and inspects ELECTRICAL and GAS permits for Chilliwack. Plumbing is usually part of the building permit.

  3. 3

    Prepare drawings and documents

    City of Chilliwack asks for: Building Permit Application Form; Two (2) complete sets of drawings: floor plans, cross-sections, foundation, elevations, plumbing, electrical, site plan, and site certificate if required (online submissions uploaded as multi-page PDFs by drawing type via ProjectDox); Site plan showing building location + dimensions, setbacks, existing/finished ground elevations, utilities (storm/water/sanitary or septic), lot grading, drainage, landscaping, driveway; applicant stakes out building location and installs temporary street-address sign; Drawings prepared by a qualified Draftsperson OR signed/sealed/dated by a Registered Professional; State of Title Certificate (proof of ownership); Letter of Authorization if an agent acts for the owner; Owner's Undertaking for Part 3 buildings using registered professionals (letters of assurance); Verification of Hazardous Materials Risk Assessment for demolition; Geotechnical report where land is subject to flooding, mudflow, erosion, etc.; New-home third-party warranty (Homeowner Protection Act / BC Housing) mandatory on new homes except owner-builders; Sealed septic filing papers where on-septic; restrictive covenants for floodplain construction.

  4. 4

    Submit your application

    MyCity Portal for online building permit applications, with ProjectDox used for drawing/document upload and review. Online submission accepted for Part 9 residential (new single/two-family, additions, renovations), rural/residential accessory, agricultural buildings, Part 3 tenant improvements, demolition, utility connection, and sign permits (pylon/fascia). New Part 3 buildings must be submitted as hard copies. Register first, then apply under Applications > Building Permit > Apply for a new permit. Online applications page: https://www.chilliwack.com/main/page.cfm?id=3198

  5. 5

    Pay the permit fee

    Per the City's 'Permit Fees and Security Deposits' schedule (based on construction value/permit type); refundable security deposits apply to certain work. Confirmed with the Building Division at application. Confirm the current schedule with Chilliwack before you budget.

  6. 6

    Plan review, then build to inspections

    The building department reviews against the BC Building Code and zoning; answer any comments quickly. Once issued, post the permit on site and book inspections at each stage — footings, framing, rough-in, insulation, final. Don't cover work before it's inspected.

What Chilliwack asks for

  • Building Permit Application Form
  • Two (2) complete sets of drawings: floor plans, cross-sections, foundation, elevations, plumbing, electrical, site plan, and site certificate if required (online submissions uploaded as multi-page PDFs by drawing type via ProjectDox)
  • Site plan showing building location + dimensions, setbacks, existing/finished ground elevations, utilities (storm/water/sanitary or septic), lot grading, drainage, landscaping, driveway; applicant stakes out building location and installs temporary street-address sign
  • Drawings prepared by a qualified Draftsperson OR signed/sealed/dated by a Registered Professional
  • State of Title Certificate (proof of ownership)
  • Letter of Authorization if an agent acts for the owner
  • Owner's Undertaking for Part 3 buildings using registered professionals (letters of assurance)
  • Verification of Hazardous Materials Risk Assessment for demolition
  • Geotechnical report where land is subject to flooding, mudflow, erosion, etc.
  • New-home third-party warranty (Homeowner Protection Act / BC Housing) mandatory on new homes except owner-builders
  • Sealed septic filing papers where on-septic; restrictive covenants for floodplain construction

Permit fees in Chilliwack

Per the City's 'Permit Fees and Security Deposits' schedule (based on construction value/permit type); refundable security deposits apply to certain work. Confirmed with the Building Division at application.

Fees change and vary by project — confirm the current schedule with City of Chilliwack.

Chilliwack permit forms

Open a form here and fill it in without leaving the page.

Pick a form to open it here.

Permit types in Chilliwack

Plumbing permit

A trade permit (often issued separately from, or alongside, the building permit) authorizing installation, extension, or alteration of potable water, drainage-waste-vent, and connections to municipal water/sewer, verified against the BC Plumbing Code.

Demolition permit

A municipal permit to tear down or remove a building or structure, conditional on safe utility disconnections, a pre-demolition hazardous-materials (asbestos) survey and abatement, and — in many cities — recycling/deconstruction requirements backed by a refundable deposit.

Worth knowing about Chilliwack

Note the distinctive chilliwack.com (not .ca) municipal domain. No formal BC Energy Step Code report was highlighted on the single/two-family requirements page (confirm current step level with the Building Division), but new-home third-party warranty is mandatory except for owner-builders. Geotech required in floodplain/erosion-prone areas (relevant near the Fraser River). Development Variance Permit needed where a zoning relaxation is required.

Chilliwack permit questions

Where do I submit a building permit application in Chilliwack?

MyCity Portal for online building permit applications, with ProjectDox used for drawing/document upload and review. Online submission accepted for Part 9 residential (new single/two-family, additions, renovations), rural/residential accessory, agricultural buildings, Part 3 tenant improvements, demolition, utility connection, and sign permits (pylon/fascia). New Part 3 buildings must be submitted as hard copies. Register first, then apply under Applications > Building Permit > Apply for a new permit. Online applications page: https://www.chilliwack.com/main/page.cfm?id=3198

Who issues electrical and gas permits in Chilliwack?

Technical Safety BC issues and inspects ELECTRICAL and GAS permits for Chilliwack. The City does NOT run its own electrical program. Apply directly to Technical Safety BC; homeowner electrical/gas permits limited to own principal residence (not suites/rentals).

How much does a building permit cost in Chilliwack?

Per the City's 'Permit Fees and Security Deposits' schedule (based on construction value/permit type); refundable security deposits apply to certain work. Confirmed with the Building Division at application. Fees vary by project, so confirm the current schedule with City of Chilliwack before budgeting.

What do I need to apply for a building permit in Chilliwack?

City of Chilliwack asks for: Building Permit Application Form; Two (2) complete sets of drawings: floor plans, cross-sections, foundation, elevations, plumbing, electrical, site plan, and site certificate if required (online submissions uploaded as multi-page PDFs by drawing type via ProjectDox); Site plan showing building location + dimensions, setbacks, existing/finished ground elevations, utilities (storm/water/sanitary or septic), lot grading, drainage, landscaping, driveway; applicant stakes out building location and installs temporary street-address sign; Drawings prepared by a qualified Draftsperson OR signed/sealed/dated by a Registered Professional; State of Title Certificate (proof of ownership); Letter of Authorization if an agent acts for the owner; Owner's Undertaking for Part 3 buildings using registered professionals (letters of assurance); Verification of Hazardous Materials Risk Assessment for demolition; Geotechnical report where land is subject to flooding, mudflow, erosion, etc.; New-home third-party warranty (Homeowner Protection Act / BC Housing) mandatory on new homes except owner-builders; Sealed septic filing papers where on-septic; restrictive covenants for floodplain construction.

Anything else to know about permits in Chilliwack?

Note the distinctive chilliwack.com (not .ca) municipal domain. No formal BC Energy Step Code report was highlighted on the single/two-family requirements page (confirm current step level with the Building Division), but new-home third-party warranty is mandatory except for owner-builders. Geotech required in floodplain/erosion-prone areas (relevant near the Fraser River). Development Variance Permit needed where a zoning relaxation is required.

Sources

General information only, not legal or code advice. Requirements vary by project and change over time — always confirm what applies to your job with City of Chilliwack before you build.